Скачать книгу

16.4, relating to payment after termination by the Contractor;

      5 clause 17.3, relating to intellectual and industrial property rights;

      6 the first paragraph of clause 17.4, relating to indemnities given by the Contractor5 ; and

      7 clause 17.5, relating to indemnities given by the Employer.

      The wording that causes most difficulty, especially to those from a non‐common law background, is the reference to indirect or consequential loss or damage. These expressions are used in the English law of contract to distinguish certain types of loss or damage and the circumstances in which the innocent party may recover compensation for them. Construction, sale and other commercial contracts often contain clauses excluding or limiting liability for consequential or indirect loss resulting from a breach.

      English law in general compensates a party for any loss which is a usual consequence of a breach of contract. Thus, if in breach of contract a builder badly installs the windows in a house he is building it is a usual consequence of his breach that damage should result to the surrounding walls by the ingress of rain water; and the building owner may be able to recover the cost of putting right that damage from the builder. Such a loss would be direct loss, flowing naturally or usually from the breach of contract.

      In some circumstances the innocent party may be able to recover damages even where a consequence of the breach of contract was unusual. An innocent party may be able to recover damages where the loss was not a usual consequence of the breach if it was, nevertheless, within the reasonable contemplation of both parties at the date of the contract that such a loss may result from the breach. Suppose that in the above example of the defective window installation the owner had intended to let the house once completed and as a result of the builder's breach of contract could not do so for some months later than he would have been able to let the house had the builder complied with the contract. If the builder had been told at the date when the contract was formed that the owner intended to let the house when completed the owner may be able to recover damages equivalent to his loss of rent for an appropriate period on the basis that such a loss was within the reasonable contemplation of both parties at that time. The loss of rental income would be indirect or consequential loss, recoverable because of the special knowledge which the builder possessed at the date of the contract which made that kind of loss within the parties' reasonable contemplation.

      The distinction between direct and consequential or indirect loss originates in a policy adopted by the common law of limiting the recoverability of compensation, or damages, for breaches of contract so that the party at fault is not held liable for any and all loss resulting from a breach, however improbable or unpredictable such a loss might be. Loss beyond the limit is regarded as ‘too remote’ to be recoverable. In the famous Victorian case of Hadley v Baxendale (1854) 9 Ex. 341 Baron Alderson said (at [354]):

      ‘Where two parties have made a contract which one of them has broken, the damages which the other party ought to receive in respect of such breach of contract should be such as may fairly and reasonably be considered either arising naturally, i.e. according to the usual course of things from such breach of contract itself, or such as may reasonably be supposed to have been in the contemplation of both parties at the time they made the contract, as the probable result of the breach of it.’

      The rule thus has two limbs:

      1 loss or damage which arises naturally, or according to the usual course of things, from the breach of contract; or

      2 loss or damage which may reasonably be supposed to have been in the contemplation of both parties at the time they made the contract as the probable result of the breach given the special circumstances known to them at the date of the contract.

      When clause 1.15/1.14 excludes liability for ‘indirect or consequential loss or damage’ it excludes liability in contract for a range of potential losses which would otherwise be recoverable if the parties had the relevant knowledge; it can be seen as confining the recoverable range to the first limb of the rule in Hadley v Baxendale.

      2.8.2 Cap on Contractor's Total Liability

      The second paragraph of clause 1.15/1.14 in the 2017 editions provides that the total liability of the Contractor to the Employer under or in connection with the Contract, other than:

      1 under clause 2.6, relating to Employer‐supplied materials and Employer's equipment;

      2 under clause 4.19, relating to temporary utilities;

      3 under clause 17.3, relating to intellectual and industrial property rights; and

      4 under the first paragraph of clause 17.4, relating to indemnities provided by the Contractor

Скачать книгу