prison must be within easy reach of a port, in order that prisoners might be landed, and conveyed rapidly and at small cost to their place of confinement.  At the same time it must not be too near an unfortified port, as such a situation would offer facilities for escape, and there would be danger of support from the sea, in the event of a general rising, and a combined attempt to restore to the fighting ranks of the enemy the thousands of captive soldiers and sailors who were in captivity hors de combat.  The site must be healthy, well supplied with water, and conveniently situated for the provision of the necessaries of life—and further, it must be near trunk roads, for convenience of administration, and in order that in the event of a rising, troops sufficient to quell the mutinous prisoners could be concentrated on the spot.

      The site chosen for the Norman Cross Depot possessed all these advantages.  It was situated on the Great North Road, one of the most important in the country, the Ermine Street of the Romans, and it was only seventy-six miles from London.  The situation was altogether suitable from a sanitary point of view, although later, at a period when the bulk were ill clad, the poor half-naked French, accustomed to a warmer climate, complained bitterly of its cold and exposed position.  An abundant supply of excellent water could be obtained by sinking deep wells, the surrounding country was agricultural, the land fertile and well stocked; there were small towns near from which supplies could be obtained, and, finally, the transports could be brought to the ports of Yarmouth, Lynn, or Wisbech, and the prisoners landed there could be cheaply conveyed by water to Yaxley, Stanground, and Peterborough, all of which places were within a few miles’ march from the prison gates.  As an alternative the prisoner could march direct from the ports to the prison.

      On the 8th December 1796 the Transport Commissioners applied to the Barrack Office for estimates for a building to contain 10,000 prisoners, but official red tape could not be disregarded, and the Barrack Master-General replied that as the Admiralty had not authorised the construction of any such buildings, he could not give any opinion on the subject.  In the Transport Office, however, were officials who recognised the urgency of the situation, and when at length on the 13th February 1797 the Barrack Master-General wrote to the Transport Board, referring to his letter of the 19th December of the previous year, and asking for an order for the building, he was too late.  The Transport Commissioners were already at work, the prison had been planned, and the work, started in the previous December, was, under the direction of William Adams, Master Carpenter to the Board of Ordnance, already making such rapid progress that portions were nearly complete.

      The material selected for the structure was wood; this was economical, and suited to the temporary character of the building.  No one, however pessimistic, thought in 1796 that the prison would be required to house prisoners of war, with only two short intervals, for another nineteen years.  Such wooden buildings, the outer walls constructed of a strong framework, with feather-edged boards overlapping one another covering and casing in the framed work, were much used in domestic architecture at this period, and many houses thus constructed may be seen in the neighbourhood of London.  A good example of a village mansion of this kind may be still seen in Lower Sydenham, where it is at present occupied by Lady Grove, the widow of Sir George Grove.  The wooden buildings were erected on a buried brick or stone foundation.

      Above all, wood lent itself to rapidity of construction, which was an urgent and essential requirement at this crisis.

      When nine years later, in 1805, fresh accommodation for the ever-increasing number of prisoners flowing into Great Britain was necessary, and Dartmoor was selected as the site for a new prison, granite was the material adopted for its construction.  The stone was obtainable on the spot, while the price of timber was prohibitive, in consequence of the blockading of the Prussian ports. 9  The granite prison at Dartmoor, commenced in 1805, received its first batch of prisoners in May 1809.  The stone building took four years to build, it served its original purpose for seven years, stood empty for thirty-four years, and is at the present time, and has been for sixty-one years, a convict prison.  The wooden buildings of Norman Cross, commenced in 1796, were ready for use in four months, served their purpose for eighteen years, and were rased to the ground in 1816.

      The earliest official information, as to the plan and the buildings of the Depot, is found in a long report by General Beathand dated 13th January 1797; later official reports and documents, paragraphs in the newspapers, and other sources of information show that the original plans were modified and expanded as the work of the prison progressed.

      The timber framework of the building was made in London, and was carted down to Norman Cross, where 500 carpenters and others were employed day and night, and seven days a week, those who would not work on Sunday being discharged.  The erection of the prisons, the accessory offices, and the barracks for the Military Guard progressed very rapidly, and on the 4th February (nine days before the Barrack Master-General applied for the order to start the work!) such progress had been made that the Admiralty instructed Mr. Poore, a surveyor, to proceed to Stilton “to survey the buildings erected near there for the confinement of prisoners of war.”  He did so, and reported that a portion of the building was already complete.  General Nicolls, the officer commanding the district, was sanguine enough to report on the 13th February that the prison at Norman Cross would be ready in about three weeks for the reception of prisoners from the citadel (Plymouth).

      This estimate of the date when the barracks would be finished was too sanguine, although the work was being carried out with all possible speed.  By the end of January the sum of £6,000 had been paid to and disbursed by Mr. Adams in wages alone. 10

      The total amount paid on account of the Norman Cross Depot up to the 19th November 1797 being so large, while the large expenditure on the alterations of old prisons and fortresses in the country was going on simultaneously, it is not surprising that on the 14th April 1797 a question was asked by an economist in the House of Commons as to the extraordinary expenditure on barracks; nor, looking to the rate at which the building of the Norman Cross Depot was being pushed forward, can we be surprised at the curt reply of the Secretary of State: “Extraordinary exertions involve extraordinary expenses.”

      There is reason to believe, however, that the question was not put without good reason.  The want of method and the overlapping of departments were not conducive to clear statements of accounts.  The action of the newly appointed Transport Board in commencing the building of the prison, while the Barrack Master was refusing to undertake this urgent work because he considered that official routine had been neglected, has already been alluded to.  The Barrack Master’s Accounts were very confused.  In the Records of the Audit Office (Roll 354, Bundle 146, Declared Accounts) the total expenditure by the Barrack Master at Norman Cross, from 1st January 1797 to Christmas 1802, is only £5,175 3s., and it is evident that the sum of £34,518 11s. 3d. does not appear in the Barrack Master’s account.  The total expenditure of his department amounted, when an inquiry was held, in 1802 to £1,324,680 12s. 5d. and there was a deficiency of £40,296 9s. 11¼d.

      Out of the confused chaos of figures there emerges the interesting fact that, between the 25th December 1796 and the 24th June 1797, £390 10s. 1d. was spent on coals supplied to the Norman Cross Depot!  A large coal bill for half a year, when we consider that in none of the blocks occupied by the prisoners, excepting the hospital blocks, was there any artificial heat.

      As the work went on, there were, as has been already stated, various alterations in the plans; thus in February and March 1797 it was ordered, that a hospital for the sick should be provided by adapting some of the blocks originally intended as prisons to this purpose, and that increased accommodation for prisoners should be obtained by adding a storey to each block in course of erection, in preference to multiplying the buildings.

      On 21st March a payment was made to Mr. Poore of £142 2s. for his services in surveying and settling the establishment at Norman Cross.  This shows that within three months from the commencement of the buildings they were in a sufficiently advanced condition to make the consideration of the necessary staff for the administration of the prison when it should be opened, a matter requiring Mr. Poore’s immediate attention.

      By the 25th March the staff had been engaged, and

Скачать книгу


<p>9</p>

  The price of timber had risen in December 1806 to £8 8s. a load; at one date the contractor complained that even by paying £12 a load he could not obtain fifty loads in Plymouth.  The Story of Dartmoor Prison, Basil Thomson.  (London: William Heinemann, 1907.)

<p>10</p>

  The sum of £14,800 was paid to Adams between the 1st January 1797 and 29th November 1797 in the following instalments:

The total amount paid to 19th November 1797 for the Norman Cross Prison was £34,518 11s. 3d., for Hull £22,600, for Lewes £12,400, and for Colchester £15,620.